This page is part of my unofficial solutions manual to the GRE Paper Practice Book (2e), a free resource available on the ETS website. They publish the questions; I explain the answers. If you haven’t worked through the Practice Book, give Section 6 a shot before reading this!
6.10: Dueling Copiers
This is a special kind of algebra problem called a work-rate problem. There is a basic procedure for these that we can follow every time. It boils down to two steps:
- Figure out the work rate of each machine (worker, factory, etc.).
- Apply those rates to solve for the target quantity.
In this problem, we have enough information to calculate each machine’s work rate directly:
What we really want to know, however, is the difference in the output of the two machines if each one runs for a specified amount of time:
So we plug in the times (which the problem provides) along with the rates we calculated:
The difference in output is
so the correct answer is (B).